During construction of the new BJ Hughes Warehouse Loadout Facility, which houses chemicals, sand and fracking materials and equipment, Braun Intertec provided concrete testing on about four acres of concrete for slab on grade and walls, verified soil bearing under construction and footings, poured column pads and poured 50-1,000 yards of concrete per day for footings and concrete paving. With a tight project schedule, Braun Intertec responded by providing support on the project 16 hours per day and wrapped up the project in three short months.
Client
Crossland Construction